LINE BLOCK (GR/SR 15.25)



Ø  Line Block means blocking any portion of the line outside station limits for the purpose of engineering works.
Ø  Where breaking the line for longer periods and involves risk, such work shall be done under Line Block.
Ø  On sections, where traffic position permits, even casual renewals may be done under Line Block.
Ø  Works like renewals of track on a bridge or an embankment etc shall be done under line block only.
Ø  JE/P.Way officials shall apply to DRM for Line block at least 24 hrs in advance.
Ø  DRM shall issue Line block order to the SMs of the Block stations and the SM shall advise the JE/P way and obtain acknowledgement.
Ø  The SM shall issue a last train certificate in triplicate to the Guard of the last train specified in the Line block order.
Ø  Caution Order shall be issued to the LP to hand over LTC to JE/P Way.
Ø  The last train shall be stopped at the site of the work by the Engineering official by the exhibition of a Stop hand signal.
Ø  Guard shall deliver one copy of the certificate to the JE/P Way and another copy to the SM at the other end.
Ø  The train need not be stopped at the site if no engineering official is available and Guard shall handover both the copies to the SM.
Ø  JE/P Way shall wait until the train clears the section.
Ø  During the period of Line block no traffic train shall be allowed to enter the block section.
Ø  Material trains, BD specials, TMM, Motor Trollies/Tower wagons may be allowed in to the section on the authority of T/A 602 as required.

Removal of Line block.
Ø  The Engineering official-in-charge of the work shall send the removal advice after the expiry of the Line block period.
Ø  If for any reason work is not completed he shall send an extension advise to the SM.
Ø  Traffic trains may be resumed on the expiry of the line block period or extension period.
Ø  Traffic trains shall be run after all the material trains or motor trollies have cleared the obstructed section.
Ø  In case SM has not received neither removal advise nor extension advise, after the expiry of the LB period traffic trains may be allowed with Caution order.
Ø  On Double lines when one line is obstructed for engineering purposes, Single line working shall be introduced until removal of Line block.
Ø  The trains running on the adjacent line shall be issued with caution order.
Ø  The engineering official shall ensure that materials do not obstruct the adjacent line.